DESIGN REVIEW APPROVAL

FORM

The Design Review Approval Form in Figure A15-1 is used to document the

completion of all the elements of a design review. While you may have documented

each of the elements (i.e., Design Review Package, Design Review, etc.)

individually, it is a good idea to have one form where all the elements are

recognized and approved. This will come in handy when you are assembling all

the data for sell-off.

F i g u r e A 1 5 - 1 — D e s i g n R e v i e w A p p r o v a l F o r m

DESIGN REVIEW APPROVAL

The ________(1)_____________ Design Review Minutes

containing the ______(1)_________Design Review Package

labeled _______(2)____________

and dated _____(3)________

and

The _________(1)___________Design Review

conducted on _____(3)__________ together with the Design Review Action Items are

hereby approved

therefore

__________(4)____________________ is hereby directed to proceed to the next stage

of the program.

Signed _____(5)________ of __________(6)______________ Date _______________

Where:

(1) The Design Review—PDR, CDR, etc.

(2) Modification or issue

(3) Date of package or event

(4) The Contractor

(5) The Customer’s Representative

(6) The Contracting Authority